Timeline

From empty block to skyline.

A multi-year journey from land acquisition to topping out — here's where the project stands and what comes next.

  1. 2019

    Site acquired

    Onni Group purchases the ~4-acre Barnes & Noble block for roughly $116M.

  2. 2022

    Approvals secured

    City of Bellevue approves the Master Development Plan and Design Review in June.

  3. 2022

    Anchor tenants move out

    Barnes & Noble relocates to Crossroads Mall and Doxa Church moves to Redmond after seven years in the former John Danz Theatre — but both buildings stay standing.

  4. 2022–2025

    Buildings stay in use

    Rather than sitting empty, the existing structures keep hosting tenants — most recently a furniture store in the former Barnes & Noble and a church in the former theatre — right up until demolition.

  5. H1 2026In progress

    Demolition

    Onni secures demolition permits and the two long-standing buildings finally come down, clearing the four-acre superblock.

  6. Jul 2026

    Excavation begins

    Groundbreaking on the 606 block kicks off a build of close to five years.

  7. ≈2030

    Targeted completion

    A roughly five-year construction program delivers all three towers.